During the summer, progress on the TREVI 1 and TREVI 2 buildings has been visible, and we are happy to see our buildings rise from week to week.

In both buildings, work is being done on the installations on the 1st floor, and in the next 2 weeks work will begin on finishing and pouring screeds.

Also in August, we will start the exterior works for water supply and sewerage. In the middle of the month we will pour the plate for the 8th floor in TREVI 1, respectively the 7th floor in TREVI 2.

Currently, the masonry installation is on the 2nd floor for the TREVI 1 building, respectively the 1st floor for the TREVI 2.